6 Downtown Beautification Project/Street Improvements.

Note from TheGardeningSnail: This page was produced by running a PDF Image File through a program that converts Image to Text. My apologies for any Textual Gremlins that may have crept in. I also may have broken up some of the longer paragraphs for ease of reading. 

Meeting Date: September 15, 2015

STAFF REPORT

AGENDA ITEM: Downtown Beautification Project/Street Improvements

MEETING DATE: September 15, 2015

PREPARED BY: Mario B. Gouveia, City Engineer

REVIEWED BY: Odi Ortiz, Interim City Manager

clip_image001

RECOMMENDATION:

Obtain direction from City Council on configuration and extent of improvements.

BACKGROUND:

The City plans to construct a renovation/beautification project in the downtown area of Main Street, from "D" to near the railroad tracks. Improvements include new sidewalks, wheelchair ramps, bulbouts at street corners, stamped concrete borders, tree wells, landscaping, landscape irrigation, decorative street lights and pavement repairs. The new facilities will meet applicable accessibility standards.

DISCUSSION:

A presentation will be made at this Council Meeting to address the proposed project scope. Staff is seeking direction from the City Council for the configuration and extent of the improvements as discussed at the two previous Council meetings.

FISCAL IMPACT:

The estimated project cost is $1,200,000.00. The project will be funded by Gas Tax (200k), TDA (400k), RSTP (450k), and 150k from a combination of funds to be determined.

ATTACHMENTS:

1. Preliminary Plans/Figures (6 sheets).

image

image

image

image

image

image