RESOLUTION: CAROLLO ENG. for Environmental Assessmt – Blueberry Crossing Commercial

Legal Disclaimer for purposes of “legal disclamerness”: This page was produced by taking an original PDF Image file and running it through a program that converted the image into text. After that, the Text File was bounced through some Blogging Software before finally ending up in my blog and then on your computer screen.

Therefore, I would not be surprised if there are a fair amount of glitches, gaffes, gremlins, and goof ups.

The purpose of this page is to give you an idea of what it going on. I’m not promising it’s perfect (software, remember?). Soooooooooo before you go “flaming” about screw-ups by City Staff, either go look at the original on the City’s Website or trot your self downtown and read the “paper version” at City Hall. 

With that in mind, on to the

RESOLUTION 2011-

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LIVINGSTON
AUTHORIZING THE ACTING CITY MANAGER TO ENTER INTO A CONTRACT WITH CAROLLO ENGINEERS FOR ENVIRONMENTAL ASSESSMENT WORK ON THE BLUEBERRY CROSSING COMMERCIAL PROJECT

WHEREAS, Phil Martin and Associates, the environmental consultant for the Blueberry Crossing Commercial Project (“Project”), has determined a need to review water distribution system and waste water collection system comments on the Project and provide clarification; and

WHEREAS, Carollo Engineers, the City’s consultant for the Water Distribution System and Waste Water Collection Master Plans, conducted a hydraulic analysis in 2007 to determine if the improvements proposed in these Master Plans needed to be revised for the Project; and

WHEREAS, Carollo Engineers has submitted a scope of work (Exhibit A) to provide clarification on that analysis; and

WHEREAS, the City Council considered the proposed scope of work at its regular meeting of January 4, 2011.

NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of Livingston hereby authorizes the Acting City Manager to enter into a contract with Carollo Engineers to provide clarification for the EIR for the Blueberry Crossing Commercial Project.

Passed and adopted this 4t` day of January 2011, by the following vote:

AYES:

NOES:

ABSENT:
ABSTAIN:

Rodrigo Espinoza, Mayor
of the City of Livingston

ATTEST:

I, hereby certify that the foregoing resolution was regularly introduced, passed and adopted at a regular meeting of the City Council of the City of Livingston this 4th day of January 2011.

Antonio Silva, City Clerk

of the City of Livingston