AGENDA
Utility Rates Stakeholders Committee Mtg Monday, April 29, 2013 at 5:30 p.m.
City Hall Conference Room
Information and Discussion
1. Solid Waste Services Update
-
The Contract with Gilton has been finalized
-
The order is in for the 2nd can is in. Cans to be delivered by June: therefore there will be no charge for the 2nd can in May.
-
The charge for May will only be for the actual Cost of Service: $15.15 (w/0 City Overhead.
-
New Rates for both cans to take affect in June: $23.79 and will be reflected in July’s billing.
-
New cans will be out prior to June 1st.
-
There will probably be a brochure attached to each can about what can/can’t go into the 2nd can.
-
Something will also be placed along with the Utility Bills explaining what is to be placed in the 2nd can.
2. Well # 8 TCP Mitigation Update
-
At 90% Plan and Specifications
-
Plans had been forwarded to California Department of Public Health (CDPH)– they have completed their review and had minor comments.
-
A letter by the consultant was prepared as a response to CDPH’s comments and will be sent out shortly.
-
Foster Farms has also reviewed the plans. They requested minor clarifications from the consultant. They did not have any major comment on the design and specifications
-
The consultant is working on two tasks: the Sewer Connection plans and Controls Design:
-
Sewer Connection plans have been completed.
-
The Control Design is in progress and should be done by next week.
-
Should be ready to bid out the project in about 4 weeks.
-
AECOM has been asked to “fast track” this project as much as possible w/o compromising the project.
3. Well # 16 Arsenic Mitigation Update
-
The contract for Media Replacement has been finalized.
-
Work to begin on May 13th and will take about 3 to 4 weeks for the Ph adjustment and equipment installation.
-
The contract for the tanks has been finalized and is currently being processed through finance.
-
There is a two week lead time for the tanks.
-
CDPH has reviewed the line diagrams (of the) process and is on board: everything is acceptable.
-
Kassie from CDPH would like to be invited while the work is going on: to look over the chemical feed systems etc.
4. Kennedy Jenks Feasibility Study Update
-
Expect to have the actual Study completed by next week sometime.
-
This would be the 2nd Revised copy that MID, CDPH, and the City has also vetted the draft.
-
Document will be presented to Stakeholders prior to being released to the General Public.
-
Stakeholders will be receiving an electronic copy and given a week or so to review it before having another meeting.
5. Report on the State Inspection
(Note from TheGardeningSnail: The link above takes you to the 2011 State Inspection Report: which was the last time the system was inspected by the State.)
-
The State comes out, reviews documentation that the City keeps: process records, operational records, etc. and goes out into the field and inspects each individual well.
-
They talk to Operations Staff: ask questions to make sure they understand what they’re doing.
-
They ask questions if they see something that might look out of place or out of line, or something new that they didn’t see at the last inspection.
-
After that, they send an evaluation with their recommendations.
-
The Department of Public Health is a Regulatory Agency that inspects the Water System.
-
Water Testing is done by Independent Laboratories: copies of lab results are sent to the City and the State.
-
Water and Waste Water (are governed by) separate Regulatory Agencies.
-
The first comment was the Overall System is in good condition.
-
They do mention the issues that we have had in the past: water quality, and more recently: water quality. These are issues of concern.
-
(along with) Finances. Those are the three areas of concern they are pointing out: cash – we have too much and we’re not spending it. (Note from TheGardeningSnail – I would hazard a guess they are referring to the TCP settlement money.)
-
There are no real surprises: things we already know: quality, quantity, and finances which will eventually need to be addressed.
-
The City already has the Official Report from the State: it was done in less than a month.
-
A copy should be up on the city’s website soon. Electronic copies will be distributed to Stakeholders.
6. Water Tank Update
-
It’s going to need some work.
-
The outside can “survive”: the inside needs to be done.
-
For the moment, the City is going to contact the Cathodic Protection people: either the ones who originally installed it, or another firm if necessary and get that redone.
-
This will be a substantial expense: not in the magnitude of a paint job, but a few thousand dollars. The divers will have to go in and pick up pieces.
-
This will be done to try to arrest further damage.
-
The comment in the inspection from 2007 was “signs of minor corrosion, blistering in floors and walls”.
-
This year the comment reads “extensive coating failure and corrosion”.
-
At this point, you cannot touch-it-up: minor repairs can be done underwater. Sandblasting and repainting the tank is a major, major project. The tank has to be drained.
-
Costs range from (on the low end) $60,000 to (on the high end) a quarter million dollars: depending on the damage.
-
This project doesn’t seem to be in the quarter million range, but it’s probably not in the lower end either: it’s somewhere in the middle.
-
These are not inexpensive repairs: the tank will need to be drained, sandblasted completely, things that need to be repaired and re-welded will have to be redone, then do the coating, then have inspections.
-
It’s all specialized (work).
-
Inspections will be stepped up. The tank will be inspected the next 2 or 3 years to see where we are.
-
The first thing that needs to be done is get the Cathodic Protection done so we can hold back the corrosion.
-
It’s the same thing with some of the other issues that we have – it comes down to finances.
-
Water valves for example: it’s 7,8 thousand dollars for a water valve replacement.
.